The dealer that I am going through for my order sent me an e-mail to let me know that the status of my order has changed. It has been changed to BX. Does anyone know what that means?
Ron
Unscheduled:
BX – good order, available for scheduling
Scheduled:
C – tentative schedule
D – firm schedule: serial number is assigned.
D1 – gateline: plant has sequenced the unit for production, estimated ship date assigned
D2 – gateline: framing and build imminent, usually within 3-6 days